Our Blog · Remodeling Permits · Malibu

Does an Interior Remodel in Malibu Need a Coastal Permit?

No, as long as the work stays inside the house and three conditions hold. The City of Malibu’s written interpretation says interior remodels are not “development” and do not require a Coastal Development Permit (CDP), provided there is no exterior work to the structure or site, no change in use that increases the intensity of the use, and no modification of a septic or water system. A Planning review is still required.

This guide follows the City’s own pages and documents as they read on November 14, 2026. It is written for Malibu homeowners planning a new kitchen or bathroom inside the house they already have.

Why the question comes up in Malibu

The City’s Local Coastal Program page says: “The entire City of Malibu is located within the California coastal zone, which means that all development and activity occurring within city limits (unless considered exempt) is subject to the regulations of the City’s Local Coastal Program (LCP).”

So for a kitchen or a bathroom, the first question is whether the work counts as development at all.

The City’s rule, in its own words

The answer is in the Planning Department’s Interpretations and Policy Manual, updated September 22, 2025. LCP Interpretation Number 1, dated March 28, 2005, asks whether interior remodels need a Coastal Development Permit. The City’s answer:

  • “No. Interior remodels are not ‘development’ and, therefore, do not require a CDP provided there is no exterior work to the structure or site, change in use that increases the intensity of the use (such as retail to restaurant), or modification of a septic/water system.”
  • “Because Interior remodels meeting these criteria are not considered development, they would also not require a CDP Exemption.”
  • “A ‘No Planning Issues’ or ‘Over-the-Counter’ review is still required.”

Read the three conditions closely. A remodel that keeps the same floor area can still fall outside this rule if it changes the outside of the house or the site. And no coastal permit does not mean no review: Planning looks at the project first.

Three things that take a remodel out of the rule

What you planWhat the City’s documents sayWho decides
Work on the outside of the house or the site, for example a new window opening or a new exterior doorThe interior rule no longer covers the project. The City keeps a separate exemption checklist for improvements to existing single-family homes.Planning Division
A change in use that increases intensity. A home kitchen rebuilt as a home kitchen keeps the same use.The City’s example is retail to restaurant.Planning Division
A change to the septic or water systemThe interior rule ends here too. The City says a coastal development permit is required for any new septic system in Malibu.Planning Division and Environmental Health

The City’s exemption checklist for single-family homes ends: “If the answer to question C, D, E, F, G or H was yes, then the project is not exempt from the requirement to obtain a coastal development permit.” Those questions include whether the structure or improvement is on a beach, in a wetland, in environmentally sensitive habitat or within 50 feet of a coastal bluff.

Which path applies to a given house is Planning’s call, not a contractor’s.

Count the plumbing fixtures before you draw

If the house is on a septic system, which the City calls an onsite wastewater treatment system (OWTS), the fixture count matters as much as the floor plan. The City’s Environmental Health FAQ says: “An upgrade of the OWTS may be required for any alteration, modification, remodel, or repair of any structure on the property that involves the addition of bedroom equivalents or plumbing fixture units which increases the wastewater load to the existing OWTS.”

The count is done on the City’s Bedroom and Fixture Unit Worksheet. Each fixture has a unit value:

  • Toilet (water closet): 6, or 3 for a 1.6 gallon flushometer tank the City has verified
  • Clothes washer: 3
  • Bathtub, shower with a single head, kitchen sink, dishwasher: 2 each
  • Wash basin (lavatory), bar sink: 1 each

On those values, a tub replaced by a shower leaves the count where it was: the tub comes off at 2 and the shower goes on at 2. A second basin for a double vanity adds 1. A new toilet adds 6 at the table value.

From the builder’s side the difference is simple. Moving a sink is plumbing work. Adding one changes the count.

A higher count does not by itself mean a new septic system: the City’s wording is “may be required”. The worksheet’s numbers may not match the permitted fixture units on file with the City, so ask City staff for the approved number for your house. The completed worksheet has to be certified by one of the professionals the City lists on it, such as an architect or a civil engineer.

The steps, in order

StepWhat happensWho does it
1. ScopeList every wall, opening and plumbing fixture you plan to change.Homeowner with the design team
2. Planning firstThe Development Portal page says: “You must have Planning approval before moving forward to Building Safety. Check in with Planning staff first and they will determine if a project is exempt from review.”Contractor or homeowner
3. Fixture countIf fixtures or bedrooms change, Environmental Health reviews whether the existing septic system can take the flow.Design team, with the professional who certifies the worksheet
4. Drawings and plan checkFor non-structural work the City asks for separate floor plans of what is existing and what is proposed. Projects in plan check go to Building Safety after Planning’s green-stamp approval.Design team
5. Stamps and permitsBuilding Safety stamps the approved plans first and Planning stamps last. Permits are then requested in the portal and sent by DocuSign to the contractor.Contractor
6. InspectionsRequested in the portal.Contractor

The City’s Uniform Application says a licensed contractor is authorized to submit an over-the-counter application and obtain permits on behalf of the property owner.

How long this takes depends on the City’s queue and on how complete the submittal is. No contractor controls that calendar, so we do not promise dates.

What needs a building permit, and what does not

The City’s Building Safety FAQ answers the common questions directly:

  • Tile and paint: “Cosmetic upgrades, such as floor tile, paint, and window coverings, do not require a permit.”
  • One permit or several: “Separate, individual permits are issued for building, mechanical, plumbing, and electrical work.” Malibu does not issue combination permits.
  • Who can obtain them: “A property owner or a licensed contractor.”

So a kitchen that moves plumbing and adds circuits involves more than one permit. As of November 2026 the Building Safety counter is open Monday through Friday from 8:00 AM to 4:00 PM (closed Wednesdays from 12:00 PM to 1:30 PM), and the Planning Division answers at 310-456-2489, ext. 485.

Five questions to ask before you hire

  1. Who checks with Planning before the plans are final? The City wants Planning approval before Building Safety.
  2. Does any part of the plan touch the outside of the house or the site? That is the first condition in the City’s interior rule.
  3. How many plumbing fixtures does the house have now, and how many after? The City counts them on its worksheet.
  4. Who obtains the separate building, plumbing, electrical and mechanical permits? Malibu does not issue combination permits.
  5. Is the CA contractor license number on the contract? You can check it on the Contractors State License Board site.

Clear answers to these five tell you the contractor has read Malibu’s rules before drawing your project.

How Mayer’s does it

Mayer’s Construction & Remodeling is a family-owned design-build company, in business since 2009, CA Lic #1063024, serving Malibu, Calabasas and Agoura Hills. For a kitchen or bathroom in Malibu:

  • We walk the house first and tell you which permit path the project is on. Planning has the final word, so we check in with Planning before the plans go to Building Safety.
  • Our in-house design team draws the plans, prepares the permit set, files it with the City of Malibu and answers the plan checkers’ corrections.
  • One licensed crew builds it, with no subcontractors, and we source the materials ourselves, with hardware and finishes rated for salt air.
  • Every mid-job change is written down and approved by you before it is built.
  • Your estimate comes after a free in-home visit.
  • See how we work in Malibu on our kitchen remodel page, https://mayerscnr.com/kitchen-remodel-malibu/, and our bathroom remodel page, https://mayerscnr.com/bathroom-remodel-malibu/. All three Los Angeles County cities we serve are on https://mayerscnr.com/los-angeles-remodeling/

FAQ

No, if it meets the City’s three conditions: no exterior work to the structure or site, no change in use that increases the intensity of the use, and no modification of a septic or water system. That is LCP Interpretation Number 1.

Yes. The same interpretation says a “No Planning Issues” or “Over-the-Counter” review is still required.

It can, if the house is on a septic system. The City says an upgrade of the system may be required when a remodel adds plumbing fixture units that increase the wastewater load. On the City’s worksheet a wash basin counts as 1 fixture unit and a toilet as 6.

No. The City’s Building Safety FAQ says cosmetic upgrades, such as floor tile, paint and window coverings, do not require a permit.

7:00 AM to 7:00 PM on weekdays and 8:00 AM to 5:00 PM on Saturdays. Construction is not allowed on Sundays or City holidays.

Free in-home estimate

Call (888) 394-4041 for a free in-home consultation.

Mayer’s Construction & Remodeling · CA Lic #1063024 · Family-owned since 2009

Mike Mayer

Project Manager, Mayer’s Construction & Remodeling · CA Lic #1063024 · Est. 2009

Scroll to Top